Street Sweeping Schedule: May – June 2026
Council’s street sweeping program will be rolling through the Shire from late May into June. Detailed cleaning is scheduled town by town below. All dates are weather permitting.
Aberdeen
- Monday 25 May - Start sweeping, approximately half done
- Monday 1 June - Finish Aberdeen
Cassilis
- Tuesday 26 May - All streets,
- Thursday 28 May - Complete remaining streets
Merriwa
- Tuesday 26 May - Start Sweeping
- Thursday 26 May Continue remaining streets
Scone - Please refer to map:
- Friday 29 May - Map 1, east of Kelly Street
- Monday 1 June - Continue Map 1, east of Kelly Street
- Tuesday 2 June - Start Map 2, west of Kelly Street
- Wednesday 3 June - Start Map 4, northeast of Map 1, all streets completed in one day
- Thursday 4 June - Continue Map 2, west of Kelly Street
- Friday 5 June - Map 3, Satur Road and streets west of Middlebrook Road, including Rosehill Road, Bunnan Road, Moobi Road and streets off Moobi Road
- Tuesday 9 June - Continue Map 2, west of Kelly Street
- Thursday 11 June - Continue Map 3
Murrurundi via Blandford
- Wednesday 10 June - Start sweeping
- Friday 12 June - Finishing remaining Streets
Catch up Periods
15 to 19 June - Crew will return to nay areas missed due to rain or heavy debris and complete all remaining work.
Please move vehicles, trailers, caravans and other items away from kerbsides where possible by using your driveway. This helps crews clean streets efficiently and thoroughly.
Thanks for helping keep our towns clean and well presented.